                      Jinsha River Xiluodu Hydropower Station
                      Time:2013-10-11 12:56:45        Word size: Small Middle Large
                       

                      Project overview:concrete hyperbolic arch dam, the maximum height of the dam is 278 meters, total installed capacity is 12.6 million kilowatts, storage capacity is 12.67 billion cubic meters. The project is currently second largest hydropower station in China.

                      Undertaken project:Cleaning works of dangerous rocks and covering layer at outlets of diversion tunnels and flood discharging tunnel at left bank, construction and support works of diversion tunnel, excavation works at inlet of diversion tunnel, tailrace surge access tunnel work at the left bank, plunge pool, afterby dam work.

                       